A Consortium of Hitachi & Somitomo of Japan declared winner of a $ 38.5 million contract for a 250 MW steam turbine for Cairo North power station extension. |
| القطاع |
Energy |
|
| تفاصيل التقرير |
A Consortium of Hitachi & Somitomo of Japan was declared winner of a $ 38.5 million contract for a 250 MW steam turbine for Cairo North power station extension. Client is CEPC – Cairo Electricity Production Co. & project consultant is Pajesco. Finance for the job is raised by Jeddah based Islamic Bank for Development. Total capacity of said extension is 750 MW. |
|
| مصدر التقرير | الاهرام | |
|
تاريخ الاعلان |